Analisis Produktivitas Alat dan Faktor yang Menghambat Produksi pada Kegiatan Pengupasan Overburden di Tambang Batubara

Authors

  • Maisa Illahi Darni Universitas Jambi
  • Hisni Rahmi Universitas Jambi
  • Lydia Kartika Basaria Sitompul Universitas Jambi
  • Qurratul Ayun Universitas Sriwijaya
  • Afni Nelvi Sekolah Tinggi Teknologi Industri Padang

DOI:

https://doi.org/10.61132/venus.v3i6.1236

Keywords:

Coal Mine, Inhibiting Factors, Overburden, Production, Productivity

Abstract

Overburden removal at Pit B did not meet the production targets for June and July 2025, which were set at 570,698.8 BCM and 400,986.56 BCM, respectively, while the actual production achieved was 507,071.66 BCM and 312,128.23 BCM. This study aims to determine the theoretical productivity of loading and hauling equipment and to identify the factors that hinder the achievement of production targets. The primary data used in this study include the cycle time of loading equipment, the cycle time of hauling equipment, bucket fill factor, and delay time. The secondary data required consist of swell factor, number of passes, bucket capacity, and available working time. The productivity of the loading equipment was 332.58 BCM/hour, while the hauling equipment achieved a productivity of 53.16 BCM/hour, with a match factor of 0.74. This indicates that the loading equipment experienced waiting time during loading operations due to the hauling equipment not operating optimally or at full capacity. The factors inhibiting the achievement of production targets include a narrow, waterlogged, and uneven working face; hard overburden material; a road grade of 16%, which exceeds the standard maximum of 12%; a curve road width of 15 m, which is less than the ideal minimum width of 19.95 m; undulating haul roads; narrow haul road width; and dusty road conditions.

References

Adha, S., Nelvi, A., & Rahmi, H. (2023). Perbandingan konsumsi bahan bakar Mitsubishi Fuso 220 pada setiap segmen jalan dan berdasarkan RPM. Jurnal Sains dan Teknologi: Jurnal Keilmuan dan Aplikasi Teknologi Industri, 23(1), 132. https://doi.org/10.36275/stsp.v23i1.604

Agung, M., Wahab, W., & Firdaus, F. (2020). Analisis kebutuhan alat gali muat dan angkut pada Blok Ulin PT Indrabakti Mustika, Kecamatan Langgikima, Kabupaten Konawe Utara. Jurnal GEOmining, 1(2), 79–88. https://doi.org/10.33387/geomining.v1i2.2406

Anggara, D., Franto, & Guskarnali. (2024). Evaluasi match factor alat gali muat dan angkut untuk meningkatkan produktivitas stripping overburden PT Cipta Kridatama. Jurnal Himasapta, 9(1), 13–20. https://doi.org/10.20527/jhs.v9i1.9373

Arisanti, R., Yanti, N., Neris, A., & Rahmi, H. (2022). Pengaruh jarak angkut terhadap fuel consumption cost. Jurnal Manajemen & Akuntansi Prabumulih, 6(2), 10–20.

Assidiqi, A., Rosalinda, & Wiratama, J. (2022). Optimalisasi produktivitas alat gali muat dan angkut pada kegiatan pengupasan overburden untuk mencapai target produksi. Jurnal Geosapta, 8(2), 165–172. https://doi.org/10.20527/jg.v8i2.13028

Frediana, Y., & Ansosry. (2019). Optimizing the production of loading digging equipment and transport equipment for overburden stripping using the queuing method and production capacity in Pit 3 PT Jambi Prima Coal, Mandiangin District. Jurnal Bina Tambang, 6(2), 157–172.

Istiqamah, D. A., & Gusman, M. (2021). Kajian teknis optimasi produksi alat gali muat dan alat angkut pada kegiatan pengupasan overburden berdasarkan efisiensi biaya operasional di Pit Barat PT Allied Indo Coal Jaya Kota Sawahlunto. Jurnal Bina Tambang, 5(1), 61–73.

Natalia, D. (2021). Penentuan nilai keserasian (match factor) untuk optimalisasi alat berat pada pekerjaan pemindahan tanah penutup pertambangan batubara PT Tri Bakti Sarimas. Jurnal Perencanaan, Sains, Teknologi, dan Komputer, 4(1), 480–491.

Nelvi, A. (2023). Analisis konsumsi bahan bakar truk Mitsubishi Fuso 220 pada pengangkutan batubara berdasarkan rimpull (Studi kasus: PT Haswi Kencana Indah). Jurnal Teknik dan Teknologi Tepat Guna, 2(1), 131–139. https://doi.org/10.62357/j-t3g.v2i1.141

Nelvi, A., & Susanti, O. (2019). Keserasian alat muat dan alat angkut untuk menunjang target produksi batubara bulan September sebesar 90.000 ton/bulan di PT Anugrah Bumi Lestari site PT Duta Alam Sumatera, Merapi Barat, Lahat, Sumatera Selatan. Jurnal Sains dan Teknologi: Jurnal Keilmuan dan Aplikasi Teknologi Industri, 19(2), 107–112. https://doi.org/10.36275/stsp.v19i2.192

Oemiati, N., Revisdah, & Rahmawati. (2020). Kinerja struktur beton bertulang berdasarkan pengujian laboratorium. BEARING: Jurnal Penelitian dan Kajian Teknik Sipil, 6(3).

Pradana, M. A., Sidiq, H., & Program Studi Teknik Pertambangan. (2022). Optimalisasi alat gali muat dan alat angkut pada lapisan tanah penutup penambangan batubara. Mining Insight, 3(1), 53–62.

Rahmi, H., & Nelvi, A. (2022). Comparison of the optimization of mechanical equipment in overburden stripping activities using the production capacity method and the overall equipment effectiveness (OEE) overburden method. Jurnal Sains dan Teknologi, 22(2), 315–326. https://doi.org/10.36275/stsp.v22i2.529

Saputra, A., Fadhly, A., Rahmi, H., Navtalia, Z., & Agustine, D. W. (2024). Optimalisasi produktivitas alat gali muat dan alat angkut menggunakan metode quality control circle (QCC) untuk mencapai target produksi batu andesit pada PT Pebana Adi Sarana. Globe: Publikasi Ilmu Teknik, Teknologi Kebumian, Ilmu Perkapalan, 2(4). https://doi.org/10.61132/globe.v2i4.679

Sarmidi, Apriansyah, Z., & Widodo, R. (2024). Analisis timbunan sementara untuk pencegahan pembakaran spontan batubara di PIT 2 Banko Barat PT Bukit Asam Tbk, Tanjung Enim, Sumatera Selatan. Jurnal Ilmiah Teknik dan Sains, 1(3), 118–125. https://doi.org/10.62278/jits.v1i3.22

Sentanu, A., Toha, M. T., & Juniah, R. (2020). Kinerja pengangkutan batubara dan overburden dalam mencapai target produksi PT Tempirai Energy Resources. Jurnal Pertambangan, 4(3). https://doi.org/10.36706/jp.v4i3.579

Winarno, E., Inmarlinianto, I., & Suretno, A. (2018). Kajian teknis produksi alat muat dan alat angkut pada pengupasan overburden tambang batubara di PT Mandiri Intiperkasa, Kalimantan Utara. Jurnal Teknologi Pertambangan, 4(2), 144–153.

Zarly, Y. F., & Kasim, T. (2018). Kajian teknis loading dan hauling produksi overburden pada tambang terbuka PT Allied Indo Coal Jaya, Parambahan, Sawahlunto. Jurnal Bina Tambang.

Downloads

Published

2025-12-31

How to Cite

Maisa Illahi Darni, Hisni Rahmi, Lydia Kartika Basaria Sitompul, Qurratul Ayun, & Afni Nelvi. (2025). Analisis Produktivitas Alat dan Faktor yang Menghambat Produksi pada Kegiatan Pengupasan Overburden di Tambang Batubara . Venus: Jurnal Publikasi Rumpun Ilmu Teknik , 3(6), 192–206. https://doi.org/10.61132/venus.v3i6.1236

Similar Articles

1 2 3 4 5 6 7 8 9 > >> 

You may also start an advanced similarity search for this article.