Analisis Manajemen Risiko Proyek dengan Metode Severity Index (SI) pada Proyek Pembangunan Gedung X Kota Surakarta

Authors

  • Ahmad Rizky Zaidan Universitas Sebelas Maret Surakarta
  • Koosdaryani Soeryodarundio Universitas Sebelas Maret Surakarta
  • Setiono Setiono Universitas Sebelas Maret Surakarta

DOI:

https://doi.org/10.61132/globe.v2i3.501

Keywords:

Risk, Severity Index (SI), Probability Impact Matrix (PIM), Risk Index

Abstract

The construction of a high-rise building is a construction project that can be said to have high risk factors so that it will have a negative effect on the project schedule, quality, and costs needed. Project risk management analysis is needed to control risks and to determine risk handling to prevent the occurrence of dominant risks in construction projects. In this study, primary data collection was carried out by distributing questionnaires, while secondary data was obtained through data from projects and literature studies. The data obtained from the questionnaire will be analyzed for risk variables using the Severity Index (SI) method. Meanwhile, the risk level analysis uses the Probability Impact Matrix (PIM). The results of the analysis show that there is a dominant risk that has the most influence on the time aspect is the risk of delay in material delivery with a high level of risk. The dominant risk that has the most influence on the cost aspect is the occurrence of equipment damage while working with a medium risk level. The dominant risk that has the most influence on the quality aspect is that the quality of the material is not in accordance with the quality specifications with a medium risk level.

References

Al-Hammad, A. M., & Sadi, A. (1996). Assessement of work performance of maintenance contractors. Journal of Management in Engineering.

Prasetyo, A. T. (2020). Analisis manajemen risiko proyek dengan metode zero-one pada proyek pembangunan gedung Kepolisian Resor Metro Bekasi. Skripsi, Universitas Sebelas Maret Surakarta.

Chapman, C. (1997). Project risk analysis and management- PRAM the generic process. International Journal of Project Management.

Chileshe, N. (2012). An evaluation of risk factors impacting construction projects in Ghana. Journal of Engineering, Design and Technology, 10(3), 306-329.

Darmayanti, C., & Nadiasa, M. (2015). Analisis dampak risiko pelaksanaan konstruksi gedung terhadap biaya, mutu, dan waktu proyek. Laporan Akhir, Universitas Udayana.

Dey, P. (2009). Managing risks of large scale construction project. Cost Engineering, 51(6), 23-27.

Prasodjo, E. K. W. (2019). Analisis manajemen risiko material dengan metode zero-one pada proyek pembangunan apartemen Tamansari Amarta Yogyakarta. Jurnal Matriks Teknik Sipil, 7(2).

Sabrina, F. (2023). Analisis manajemen risiko dampak kecelakaan kerja pada proyek konstruksi jembatan beton dengan standar AS/NZS 4360:2004. Jurnal Matriks Teknik Sipil, 11(4).

Fisk, E. R., & Reynolds, W. D. (2014). Construction project administration. New Jersey: Pearson.

Flanagan, R., & Norman, G. (1993). Risk management and construction. New York: Blackwell Science.

Haryono, S. (2012). Metodologi penelitian bisnis & manajemen teori & aplikasi. Jakarta: PT IPU.

Hawari, K. (2009). Identifikasi risiko proyek pada tahap konstruksi bangunan bertingkat 4-20 lantai di Jabodetabek dari sudut pandang kontraktor. Skripsi, Universitas Indonesia.

Ghozali, I. (2009). Aplikasi analisis multivariate dengan program SPSS. Semarang: Badan Penerbit Universitas Diponegoro.

Soeharto, I. (1999). Manajemen proyek dari konseptual sampai operasional. Jakarta: Penerbit Erlangga.

Sofiana, I. (2022). Analisis manajemen risiko pelaksanaan pembangunan proyek konstruksi bangunan gedung bertingkat (studi kasus: Proyek pembangunan Hotel Loji di Boyolali). Jurnal Matriks Teknik Sipil, 10(3).

Kendrick, T. (2009). Identifying and managing project risk: Essential tools for failure-proofing your project. New York: Amacom.

Kerzner, H. (2009). Project management: A system approach to planning, scheduling, and controlling. New York: John Wiley & Sons Inc.

Knight, K., & Fayek, A. R. (2002). Use of fuzzy logic for predicting design cost overruns on building projects. Journal of Construction Engineering and Management.

Majid, A., & McCaffer, R. (1997). Assessment of work performance of maintenance contractors in Saudi Arabia. Journal of Management in Engineering.

Mulyarko, L. G., Hartono, W., & Sugiyarto. (2015). Analisis pengaruh risiko pada kontrak kerja konstruksi terhadap biaya pekerjaan konstruksi pada proyek pembangunan jalan tol Bogor Ring Road Seksi II A. Jurnal Matriks Teknik Sipil, 3(2).

PMI. (2013). A guide to the project management body of knowledge (PMBOK) (5th ed.). Project Management Institute, Inc.

Saputro, C. (2022). Analisis manajemen risiko proyek bangunan gedung bertingkat dengan metode severity index. Journal of Civil Engineering, Building and Transportation, 6(2), 140-147.

Sugiyono. (2013). Metode penelitian kuantitatif, kualitatif, dan R&D. Bandung: Penerbit Alfabeta.

Zayed, T., Amer, M., & Pan, J. (2008). Assessing risk and uncertainty inherent in Chinese highway projects using AHP. International Journal of Project Management.

Zou, P., & Couani, P. (2012). Managing risks in green building supply chain. Architectural Engineering and Design Management, 8(2), 143-158.

Downloads

Published

2024-08-07

How to Cite

Ahmad Rizky Zaidan, Koosdaryani Soeryodarundio, & Setiono Setiono. (2024). Analisis Manajemen Risiko Proyek dengan Metode Severity Index (SI) pada Proyek Pembangunan Gedung X Kota Surakarta. Globe: Publikasi Ilmu Teknik, Teknologi Kebumian, Ilmu Perkapalan, 2(3), 211–221. https://doi.org/10.61132/globe.v2i3.501

Similar Articles

1 2 > >> 

You may also start an advanced similarity search for this article.