Analisis Keterlambatan dalam Pelaksanaan Proyek Konstruksi Rumah Hunian Dempsey Hill, Citraland Utara, Kota Surabaya

Authors

  • Yafie Abdillah Akbar Institut Teknologi Sepuluh Nopember
  • Ridho Bayu Aji Institut Teknologi Sepuluh Nopember
  • Gentur Prihartono Institut Teknologi Sepuluh Nopember
  • Muhammad Sigit Darmawan Institut Teknologi Sepuluh Nopember
  • Budi Suswanto Institut Teknologi Sepuluh Nopember

DOI:

https://doi.org/10.61132/konstruksi.v3i3.983

Keywords:

Construction Management, Dempsey Hill, Factor Analysis, Project Delay, Residential House

Abstract

This journal examines the factors that have the potential to cause delays in the implementation of the Dempsey Hill residential housing construction project, North Citraland, Surabaya. Projects managed by CV. Tirta Kusuma has a target of completion in 10 months, but there are indications of delays that affect the schedule and costs. This study aims to identify and analyze the dominant factors causing delays, such as project management, material procurement, and human resources. The methods used include observation, questionnaire distribution, and literature study. The results of this analysis are expected to provide recommendations to improve time management, resource efficiency, and control of future construction projects. The results of data analysis in this study indicate that project delays are primarily caused by material delays and errors in work execution, as concluded based on the results of factor analysis.

References

Agritama, R. P., Huda, M., & Rini, T. S. (2018). Faktor–faktor yang mempengaruhi keterlambatan proyek konstruksi di Surabaya. Axial: Jurnal Rekayasa dan Manajemen Konstruksi, 6(1), 25–32.

Alaghbari, W., Kadir, M. R. A., Salim, A., & Ernawati, A. (2007). The significant factors causing delay of building construction projects in Malaysia. Engineering, Construction and Architectural Management, 14(2), 192–206. https://doi.org/10.1108/09699980710731308

Ariefasa, R. (2011). Faktor penyebab keterlambatan pekerjaan konstruksi bangunan gedung bertingkat yang berpengaruh terhadap perubahan anggaran biaya pada pekerjaan struktur (Skripsi, Universitas Indonesia).

Assaf, S. A., & Al-Hejji, S. (2006). Causes of delay in large construction projects. International Journal of Project Management, 24(4), 349–357. https://doi.org/10.1016/j.ijproman.2005.11.010

Dipohusodo, I. (1996). Manajemen proyek dan konstruksi (Jilid 1). Kanisius.

Djuniadi, A. (2016). Buku statistik inferensial. Universitas Negeri Semarang.

Fansuri, S. (2014). Penyebab terjadinya keterlambatan waktu penyelesaian proyek konstruksi di Dinas PU Bina Marga Kabupaten Sumenep. Jurnal Ilmiah MITSU (Media Informasi Teknik Sipil Universitas Wiraraja), 2(2), 1–9.

Faridi, A. S., & El-Sayegh, S. M. (2006). Significant factors causing delay in the UAE construction industry. Construction Management and Economics, 24(11), 1167–1176. https://doi.org/10.1080/01446190600827033

Kaming, P. F., Olomolaiye, P. O., Holt, G. D., & Harris, F. C. (1997). Factors influencing construction time and cost overruns on high-rise projects in Indonesia. Construction Management and Economics, 15(1), 83–94.

Kasman, R., & Handayani, A. T. (2020). Analisis faktor penyebab keterlambatan proyek konstruksi menggunakan metode RII (Relative Importance Index). Jurnal Teknik Sipil ITN Malang, 27(1), 25–33.

Priyatno, D. (2010). Buku 5 jam belajar olah data dengan SPSS 19. Andi.

Sambas, M. A., & Firmansyah, D. (2021). Evaluasi faktor-faktor penyebab keterlambatan proyek konstruksi menggunakan metode FMEA (Failure Mode and Effect Analysis). Jurnal Teknik Sipil dan Lingkungan, 5(2), 67–76.

Soehendradjati, R. J. B. (1987). Manajemen konstruksi. Gadjah Mada University Press.

Suharto, R. (2001). Manajemen proyek dari konseptual sampai operasional. Erlangga.

Tumi, S. A. H., Omran, A., & Pakir, A. H. K. (2009, November). Causes of delay in construction industry in Libya. In The International Conference on Economics and Administration (pp. 265–272).

Widodo, S., & Sari, N. A. (2017). Faktor dominan penyebab keterlambatan proyek konstruksi di Kabupaten Jember. Jurnal Teknik Sipil Universitas Jember, 4(2), 50–58.

Downloads

Published

2025-07-14

How to Cite

Yafie Abdillah Akbar, Ridho Bayu Aji, Gentur Prihartono, Muhammad Sigit Darmawan, & Budi Suswanto. (2025). Analisis Keterlambatan dalam Pelaksanaan Proyek Konstruksi Rumah Hunian Dempsey Hill, Citraland Utara, Kota Surabaya. Konstruksi: Publikasi Ilmu Teknik, Perencanaan Tata Ruang Dan Teknik Sipil, 3(3), 278–287. https://doi.org/10.61132/konstruksi.v3i3.983