Analisis Akar Masalah Keterlambatan Pengerjaan pada Proyek Konstruksi Politeknik Maritim Negeri Indonesia

Authors

  • Naufal Iman Adzhan Universitas Sebelas Maret
  • Ary Setyawan Universitas Sebelas Maret
  • Koosdaryani Soeryodarundio Universitas Sebelas Maret

DOI:

https://doi.org/10.61132/venus.v2i6.647

Keywords:

Project Delays, Construction Industry, Causes Of Delays.

Abstract

The construction industry in Indonesia is growing rapidly, playing a crucial role in the country's economic, political, and social development. However, alongside this rapid growth, issues such as project delays are inevitable. The construction project of the Indonesian Maritime Polytechnic, for instance, has experienced significant delays, which can lead to increased costs, waste of human resources, and disputes among the involved parties. Understanding the primary causes of these delays is essential for developing effective strategies to avoid future delays. This analysis uses both qualitative and quantitative methods to identify the root causes of delays. Data was collected through surveys of respondents involved in the project, including project managers, field staff, and consultants. The analyzed causes of delays include insufficient funding, increases in raw material costs, additional costs, contract document errors, poor communication, and slow decision-making. To minimize delays and their impacts, several recommendations can be made: effective strategic planning, improved communication, increased staff, accurate initial cost estimates, and good management. By implementing these recommendations, the Indonesian Maritime Polytechnic construction project can be completed more effectively and efficiently, and future delays can be avoided.

References

Alzara, M., Kashiwagi, J., Kashiwagi, D., & Al-Tassan, A. (2016). Using PIPS to minimize causes of delay in Saudi Arabian construction projects: University case study. Procedia Engineering, 145, 932-939. doi: 10.1016/j.proeng.2016.04.121

Awari, S., Jamgade, M., & Patil, U. (2016). Identifying the cause of delay in construction industry in Mumbai region. International Journal of Modern Trends in Engineering, 2(7), 539-543.

Chandra Pratama Putra, J., & Ade Asmi. (2017). Aplikasi structural equation modeling dalam analisis faktor-faktor penyebab keterlambatan penyelesaian proyek konstruksi di Indonesia. Rekayasa Sipil, 6(2), 113-122.

Gajare, Y., & Attarde, P. (n.d.). Analysis of delay causes in residential construction projects.

James, O. D., Lekan, A. M., & O, O. C. (2014). Causes and effect of delay on project construction delivery time. International Journal of Education and Research, 2(4).

Kasimu, A. M., & Isah, A. D. (2012). Causes of delay in Nigeria construction industry.

Kesavan, M., Gobidan, N. N., & Dissanayake, P. B. G. (2015). Planning & mitigation methods to reduce the project delays in Sri Lankan civil engineering construction industries.

Omran, A., Ling, O. A., Pakir, A. H. K., & Ramli, M. (2010). Delays factors in construction projects development: The case of Klang Valley, Malaysia. Journal of Academic Research in Economics, 2(2).

Pourrostam, T., & Ismail, A. (2011). Study of methods for minimizing construction delays: Evidences from a developing country. Advanced Materials Research, 201-203, 2939-2942.

Sambasivan, M., & Soon, Y. W. (2007). Causes and effects of delays in Malaysian construction industry. International Journal of Project Management, 25(5), 517-526. doi: 10.1016/j.ijproman.2006.11.007

Sumaiyya, N., & Pranay, K. (2013). Causes of delays in any construction project. International Journal of Science and Research, 5.

Tilahun, S. (2016). Cause and effects of delay on educational building projects in Addis Ababa University case study. Addis Ababa University, Addis Ababa, Ethiopia.

Trauner, T. J. (2009). Construction delays: Understanding them clearly, analyzing them correctly. Butterworth-Heinemann.

Wei, K. S. (2010). Causes, effects and methods of minimizing delays in construction projects. A Project Report.

Wirabakti, D. M., Abdullah, R., & Maddeppungeng, A. (n.d.). Studi faktor-faktor penyebab keterlambatan proyek konstruksi bangunan gedung.

Downloads

Published

2024-12-12

How to Cite

Naufal Iman Adzhan, Ary Setyawan, & Koosdaryani Soeryodarundio. (2024). Analisis Akar Masalah Keterlambatan Pengerjaan pada Proyek Konstruksi Politeknik Maritim Negeri Indonesia . Venus: Jurnal Publikasi Rumpun Ilmu Teknik , 2(6), 201–212. https://doi.org/10.61132/venus.v2i6.647

Similar Articles

1 2 3 4 5 > >> 

You may also start an advanced similarity search for this article.