Analisis Perbandingan Optimasi Pit 24 dengan Metode Lerch Grossman 2D terhadap Estimasi dari Software Minescape di PT Indominco Mandiri (IMM), Kabupaten Kutai Timur, Provinsi Kalimantan Timur
DOI:
https://doi.org/10.61132/globe.v3i3.947Keywords:
pit limit, profit, lerch grossman, minescape 5.7Abstract
An open pit exploitation activity will become less effective and cause production to not run well, resulting in the failure to meet production targets at PT. Indominco Mandiri. Therefore, to achieve production targets and obtain more optimal results, we need to plan the Design Pit Limit. The purpose of this research is to optimize the pit, find the BESR value, and compare the differences between two methods. The Lerch Grossman 2D algorithm method is believed to be able to determine the optimal pit boundary quite quickly, while the Minescape with its triangle method can calculate some unreadable sides quite accurately. The Lerch Grossman method with its economic blocks indicates that an elevation of 72 mdpl is the outer boundary of the pit that has the potential to generate a profit of $20,194,836.59, with the best consideration being a Stripping Ratio of 1:21.08. With that lower limit, an optimal pit design was created using minescape software, resulting in a coal reserve value of 1,581,870.42 tons with a profit of $14,590,646.75, which is larger and with a smaller SR of 1:19.06.
References
Alfiyanda, A. (2023). Perancangan triwulan sequence penambangan batubara pada pit SF PT. Wijaya Mandiri Energi. Jurnal Sosial dan Teknologi, 3(12).
Cuba, M. A. (2011). An approach pit optimization methodology suited to the SCM framework. CGS Annual Report.
Dimitrakopoulos, R. (2014). Optimized open pit mine design, pushback, and the gap problem. Journal of Mining Science, 50(3).
Dzakir, L., Akbar, F., & Yusuf, M. (2024). Rekayasa perencanaan tambang. Tohar Media.
Edward, A. C. (2001). Mineral resource and ore reserve estimation. The Australian Institute of Mining and Metallurgy.
Gocht, W. R. (1988). International mineral economics. Springer-Verlag Berlin Heidelberg.
Hardiman, V., Siregar, R., & Fadhlurrahman, M. (2024). Pemilihan optimum pit limit berdasarkan volatilitas harga batubara menggunakan discounted cash flow. Jurnal Pertambangan, 8(1).
Hartman, H. (1992). SME mining engineering book (2nd ed., Vol. 1). Society for Mining, Metallurgy, and Exploration, Inc.
Hartman, H. (2002). Introductory mining engineering. Wiley-India.
Hidayatullah, M., Rinaldi, A., & Farhan, R. (2016). Penentuan pit limit penambangan batubara dengan metode Lerch Grossman menggunakan 3D mine software. Kurvatek, 1(2).
Hustrulid, W., Kuchta, M., & Martin, R. K. (2013). Open pit mine planning & design (3rd ed., Vol. 1). CRC Press.
Kennedy, B. A. (1990). Surface mining (2nd ed.). SME.
Laporan akhir kajian hidrologi & hidrogeologi di area pertambangan batubara West Block PT. Indominco Mandiri. (n.d.). Bontang.
Mawendri, H. (2023). Geologi pola sebaran batubara di WIUP PT. Manda Akini Mandiri Makmur Desa Rawa Mekar Kecamatan Maro, Sebo Ulu [Skripsi, Universitas Jambi].
Muchlis, V. (2019). Modul pemodelan geologi batubara menggunakan software Minescape. Yogyakarta.
Nurhakim. (2008). Draft bahan kuliah perencanaan dan pemodelan tambang. Universitas Lambung Mangkurat.
Osanloo, M. (2000). Using 2D Lerch and Grossman algorithm to design final pit limits of Sungun Copper Deposit of Iran. Technical Note Dept. of Mining and Metallurgy, University of Technology Tehran.
Pangestu, W. (2022). Kajian optimasi pit pada penambangan andesit menggunakan metode Lerch Grossman [Skripsi, UPN Yogyakarta].
Rifandy, A., Prasetyo, B., & Hakim, R. (2018). Optimasi pit tambang terbuka batubara dengan pendekatan incremental pit expansion, BESR, dan profit margin. Jurnal Geologi Pertambangan, 2(24).
Sulystiana, S., & Waterman, B. (2018). Perencanaan tambang. Kilaubook.
Vernando, G. (2024). Analisa studi kelayakan ekonomis penambangan dan kebutuhan alat penambangan batubara di Pit IV PT. Tambang Bukit Tambi site Padang Kelapo, Kabupaten Batanghari, Provinsi Jambi. Jurnal Bina Tambang, 4(2).
Wiwin, W. (n.d.). Analisis batas penambangan optimal batubara menggunakan metode algoritma Lerch Grossman 2D pada PT Metalindo Bumi Raya. Jurnal Himasapta, 5(1).
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2025 Globe: Publikasi Ilmu Teknik, Teknologi Kebumian, Ilmu Perkapalan

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.



