Analisis Peran Manajer Lapangan dalam Optimalisasi Manajemen Sumber Daya Manusia pada Proyek Konstruksi di Kota Malang
DOI:
https://doi.org/10.61132/konstruksi.v4i1.1337Keywords:
Construction Project, Human Resource Management, Leadership, Site Manager, Workforce PlanningAbstract
This research looks into how site managers in construction projects in Malang City manage and improve their use of human resources. The research is driven by the significance of effective human resource management in ensuring project success and the lack of studies focusing on the operational strategies of site managers within a local context. This study uses a quantitative method that is both descriptive and analytical. It involves giving out a survey to 40 people, including site managers, contractors, and foremen. The independent variables include leadership and supervisory style, human resource planning and workforce allocation, training and competency development, team communication and coordination, performance monitoring and evaluation, as well as motivation and welfare. The dependent variable is the degree to which human resource management is optimized. The results of validity and reliability tests indicate that all research instruments are valid and reliable. Multiple linear regression analysis shows that leadership and supervisory style, along with human resource planning and workforce allocation, have a significant partial effect on improving HRM practices. Other variables have a positive but statistically insignificant partial effect on the estate. Overall, the management of human resources in construction projects in Malang City is considered to be fairly good. This study confirms that leadership and workforce planning are the main strategic factors for site managers in improving the effectiveness of human resource management in construction projects.
References
Bunyamin, B., Pramanda, H., Diara, W., & Sarana, D. (2024). Analisis pengaruh pengalaman dan karakter sumber daya manusia terhadap kualitas kerja proyek konstruksi. Tameh, 13(1), 55–66. https://doi.org/10.37598/tameh.v13i1.145
Fobiri, G., Musonda, I., & Muleya, F. (2025). Using reality capture technology for efficient cost valuation and work verification of construction projects. Construction Innovation, 25(7), 50–75. https://doi.org/10.1108/CI-08-2024-0223
Gunasti, A. (2020). Penerapan manajemen sumber daya manusia pada tenaga kerja konstruksi yang tidak bersertifikat. Jurnal Inovasi Penelitian, 1(3), 1–4. https://doi.org/10.47492/jip.v1i5.182
Irawan, D. (2025). Transformasi kepemimpinan dan motivasi kerja dalam meningkatkan kinerja konstruksi berkelanjutan. https://books.google.co.id/books?id=N71QEQAAQBAJ
Irawan, D., Mochtar, I. B., & Utomo, C. (2019). The actualization of leadership models adopted by field implementers that influencing the contractor employees' motivation and performance. Journal of Applied Engineering Science, 17(4), 555–566. https://doi.org/10.5937/jaes17-21908
Nurhendi, R. N., & Bastam, M. N. (2024). Tinjauan faktor utama yang mempengaruhi produktivitas tenaga kerja pada proyek konstruksi dengan pendekatan peringkat relative importance index (RII). Deformasi, 9, 167–177. https://doi.org/10.31851/deformasi.v9i2.17136
Pramono, B., Khadavi, K., & Peli, M. (2024). Pengaruh kompetensi manajer proyek terhadap kinerja waktu penyelesaian proyek konstruksi di Kota Payakumbuh. Sigma Teknika, 7(2), 420–427. https://doi.org/10.33373/sigmateknika.v7i2.6750
Pratama, N. M. F., & Chalid, A. (2024). Pengaruh kebijakan project manager terhadap motivasi tenaga kerja pada pelaksanaan proyek konstruksi. Sistem Infrastruktur Teknik Sipil (SIMTEKS), 4(1), 23–34. https://doi.org/10.32897/simteks.v4i1.3035
Purwadi, A. (2024). The effect of transformational leadership on team performance on construction projects. International Journal of Management Science and Information Technology, 4(1), 129–136. https://doi.org/10.35870/ijmsit.v4i1.2679
Sandberg, R., & Löwstedt, M. (2025). The happily overworked professional: Unpacking the autonomy paradox in excessive work regimes amongst construction site managers. Safety Science, 184. https://doi.org/10.1016/j.ssci.2024.106760
Silalahi, J. F., Simanjuntak, P., & Tampubolon, S. P. (2022). Pengaruh kepemimpinan project manager dan kinerja supply chain terhadap keberhasilan proyek konstruksi. Jurnal Rekayasa Teknik Sipil dan Lingkungan (CENTECH), 3(1), 34–45. https://doi.org/10.33541/cen.v3i1.3872
Sudariana, N., & Yoedani. (2021). Analisis statistik regresi linier berganda.
Sugiyono. (2013). Metode penelitian kuantitatif, kualitatif dan R&D (13th ed.). Alfabeta.
Yusuf, R. (2022). Mengetahui penyebab profesional manajer proyek dalam kegiatan proyek konstruksi. Tolis Ilmiah: Jurnal Penelitian, 4(1), 43–50. https://doi.org/10.56630/jti.v4i1.211
Zakyahutami, F. R., Abduh, M. N., & Mulyani, S. P. (2025). Analisis produktivitas tenaga kerja perhitungan lapangan pada konstruksi bangunan gedung pada pembangunan gedung mall pelayanan publik Kabupaten Gowa – Sulawesi Selatan. Jurnal Pengembangan Teknik Sipil dan Konstruksi, 3(2), 140–148. https://doi.org/10.56326/jptsk.v3i2.4699
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 Konstruksi: Publikasi Ilmu Teknik, Perencanaan Tata Ruang dan Teknik Sipil

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.