Metode Pelaksanaan Perbaikan Tanah Menggunakan Metode Preloading dan Prefabricated Vertical Drain (PVD) Pada Pembangunan Jalan Lingkar Utara Lamongan

Authors

  • Denis Tiyas Ayu Saputri Universitas 17 Agustus 1945 Surabaya
  • Fiarestu Wahyu Dewanti Universitas 17 Agustus 1945 Surabaya
  • Raihan Bryne Firdaus Al Machrus Universitas 17 Agustus 1945 Surabaya
  • Syahrizal Abdullah Razak Universitas 17 Agustus 1945 Surabaya
  • Dika Ayu Safitri Universitas 17 Agustus 1945 Surabaya

DOI:

https://doi.org/10.61132/venus.v2i2.268

Keywords:

Soil improvement, construction implementation method, Preloading, Prefabricated Vertical Drain (PVD)

Abstract

The construction implementation method is a very important part of the construction project to obtain the objectives of the project, the cost, quality and time. The technology aspect is very important in a construction project. Using the method of proper, practical, fast, and safe is very helpful in a construction project. Preloading and Prefabricated Vertical Drain (PVD) methods are intended to accelerate settlement and increase the bearing capacity of soft native soils by reducing pore water through PVD in the soil with the intention of reducing water content or air content in soil grains so as to accelerate long-term settlement. Preloading with PVD can reduce the material used for pre-loading, reduce embankment material, accelerate consolidation time, and increase embankment stability.

References

Adinegoro, C., Sholeh, M., Novianto, D., Manajemen, M., Konstruksi, R., Sipil, J. T., … Sipil, T. (2021). METODE PELAKSANAAN PERBAIKAN TANAH MENGGUNAKAN METODE PRELOADING DAN PREFABRICATED VERTICAL DRAIN (PVD) PADA TERMINAL INTERNASIONAL KIJING PONTINAK (Vol. 2). Diambil dari http://jos-mrk.polinema.ac.id/

Aspar, W. A. N., & Fitriani, E. N. (2023). PENGARUH JARAK DAN POLA PREFABRICATED VERTICAL DRAIN (PVD) PADA PERBAIKAN TANAH LEMPUNG LUNAK = EFFECT OF DISTANCE AND PATTERN OF PREFABRICATED VERTICAL DRAIN FOR IMPROVEMENT OF SOFT CLAY SOIL. Majalah Ilmiah Pengkajian Industri, 10(1). https://doi.org/10.29122/mipi.v10i1.102

Fitriani, E. N. (t.t.-a). NILAI PRODUKTIVITAS PREFABRICATED VERTICAL DRAIN MENGGUNAKAN METODE TIME STUDY.

Fitriani, E. N. (t.t.-b). NILAI PRODUKTIVITAS PREFABRICATED VERTICAL DRAIN MENGGUNAKAN METODE TIME STUDY.

Fitriani, E. N., & Susetyo, B. (2019). IMPLEMENTASI JARINGAN SYARAF TIRUAN (JST) PADA PRODUKTIVITAS PEKERJAAN PREFABRICATED VERTICAL DRAIN. Rekayasa Sipil, 7(2), 71. https://doi.org/10.22441/jrs.2018.v07.i2.02

Gregorius Sandjaja, dan. (2023a). METODE PERBAIKAN TANAH DENGAN PREFABRICATED VERTICAL DRAIN (PVD) PADA JALAN TOL SERPONG-BALARAJA SEKSI 1B (Vol. 6).

Gregorius Sandjaja, dan. (2023b). METODE PERBAIKAN TANAH DENGAN PREFABRICATED VERTICAL DRAIN (PVD) PADA JALAN TOL SERPONG-BALARAJA SEKSI 1B (Vol. 6).

Husni Malik Hasibuan, M., Pasaribu, B., & Ingriyana Utami, F. (t.t.). PERENCANAAN PERBAIKAN TANAH LUNAK MENGGUNAKAN METODE PRELOADING DAN PREFABRICATED VERTICAL DRAIN (PVD) PADA PROYEK PEMBANGUNAN JALAN TOL TRANS SUMATERA SEKSI TEBING TINGGI-INDERAPURA. Dalam JTSIP (Vol. 1).

Ranty, O. G., & Andayono, T. (2021). PERBAIKAN TANAH DENGAN METODE PREFABRICATED VERTICAL DRAIN PADA PROYEK JALAN TOL SEMARANG-DEMAK SEKSI 2 (Vol. 8). Diambil dari http://ejournal.unp.ac.id/index.php/cived/index

Downloads

Published

2024-04-22

How to Cite

Denis Tiyas Ayu Saputri, Fiarestu Wahyu Dewanti, Raihan Bryne Firdaus Al Machrus, Syahrizal Abdullah Razak, & Dika Ayu Safitri. (2024). Metode Pelaksanaan Perbaikan Tanah Menggunakan Metode Preloading dan Prefabricated Vertical Drain (PVD) Pada Pembangunan Jalan Lingkar Utara Lamongan. Venus: Jurnal Publikasi Rumpun Ilmu Teknik , 2(2), 150–157. https://doi.org/10.61132/venus.v2i2.268

Similar Articles

<< < 4 5 6 7 8 9 

You may also start an advanced similarity search for this article.