Analisis Delay Time Alat Angkut untuk Mengurangi Antrian Timbangan dari 80 Menit Menjadi 20 Menit pada Kegiatan Pengangkutan Batubara pada PT. Saptaindra Sejati
DOI:
https://doi.org/10.61132/venus.v2i6.617Keywords:
Production, Delay Time, Loss, Fishbone, ScalesAbstract
At this time the delay time that occurs on the DT-30T conveyance is 174 minutes and the DT-40T is 188 minutes. The biggest cause of delay time is the queue at the scales, namely on the DT-30T it is 80 minutes and the DT-40T is 85 minutes, thus causing actual productivity. The DT-30T was only 5.6 tons/hour and experienced a production loss of 0.4 tons/hour and the actual productivity of the DT-40T was only 6.9 tons/hour and experienced a production loss of 1.1 tons/hour. The aim of this research is to analyze the amount of delay time, production loss before and after improving the queue on the scales and how to reduce the queue time for scales on the DT-30T and DT-40T transportation equipment After processing the data, we obtain the Delay time on the DT-30T transport equipment after repairs the weighing queue is 33 minutes and the DT-40T is 28 minutes. The actual production of DT-30T after improvements to the weighing queue was 7 tons/hour and there was no production loss. Meanwhile, the actual production of the DT-40T after repairs was 9 tons/hour and there was no production loss.
References
Anisari Rezky, (2016), Produktivitas Alat Muat Dan Angkut Pada Pengupasan Lapisan Tanah Penutup Di Pit 8 Fleet Di PT Jhonlin Baratama Jobsite Satui Kalimantan Selatan. Jurnal Intekna, Vol. 16, No. 1. Tahun 2016. Page 77-81.
Ervil, Riko, Tri Ernita, Yaumal Arbi, (2016), Buku Panduan Penulisan dan Ujian Skripsi , Sekolah Tinggi Teknologi Industri (STTIND) Padang.
Fajri Aldi, Mulya Gusman, (2021), Optimalisasi Kinerja Alat Gali Muat Dan Alat Angkut Untuk Mencapai Target Produksi Overburden Menggunakan Metode Quality Control Circle Di Pit 1 Timur Pada Tambang Terbuka PT Allied Indo Coal Jaya, Parambahan, Sawahlunto, Sumatera Barat. Jurnal Bina Tambang, Vol. 6, No. 4.. Page 1-10.
Ilahi Riki Rizki, E. Ibrahim, Fuad Rusydi Swardi,Teknis Produktivitas Alat Gali-Muat (Excavator) Dan Alat Angkut (Dump Truck) Pada Pengupasan Tanah Penutup Bulan September 2013 Di PIT 3 Banko Barat PT Bukit Asam (Persero) TBK. UPTE. Jurnal Ilmu Teknik, Vol. 13, No. 1. Page 1-9.
Irwan Edel Frudis S, Janiar Pitulima, Mardiah. (2018), Kajian Teknis Alat Gali Muat dan Alat Angkut pada Pencapaian Pengupasan Overburden 1.120.000 BCM di Pit Taman Tambang Air Laya Bulan September 2016 PT Bukit Asam (Persero) Tbk.. Jurnal Mineral, Vol. 3 (1). Halaman 1-8.
M. Rafles Yusuf, Yoszi Mingsi, Riko Malyudi Aneptra.(2018), Optimalisasi Produksi Alat Muat pada Pengupasan Lapisan Tanah Penutup dengan Menggunakan Metode Overall Equipment Effectivenes (OEE) Tahun 2018 di Blok B PT Minemax Indonesia, Kabupaten Mandiangin Provinsi Jambi. Jurnal Bina Tambang, Vol. 4, No. 3. Tahun 2018. Halaman 98-108.
Natasha Nur Ananda, Yoszi Mingsi Anapetra, (2019) Evaluasi Efisiensi Alat Gali-Muat Terhadap Produktivitas Setelah Delay Shift Change pada Pembongkaran Overburden Bulan Februari 2019 di Pit AB RTS (Roto South) Tambang Batubara PT Bukit Makmur Mandiri Utama Jobsite PT Kideco Jaya Agung. Jurnal Bina Tambang, Vol. 4, No. 4. Halaman 1-12.
Oemiati Nurnilam, Revisdah, Rahmawati, (2020), Analisa Produktivitas Alat Gali Muat Dan Alat Angkut Pada Pengupasan Lapisan Tanah Penutup (Overburden). Jurnal Teknik, Vol. 6, No. 3. Page 1-9.
Prodjo Sumarto, Partanto, (1995), Pemindahan Tanah Mekanis, Institute Teknologi Bandung
Rahayu, dan Siska, Murad M.S.(2019), Perencanaan Kebutuhan Alat Gali Muat dan Alat Angkut Batukapur di Area Pit Limit pada Tambang Quarry PT Semen Padang, Sumatera Barat. Jurnal Bina Tambang, Vol. 5 No. 1. Page 212-224.
Saliman, Hermanto, Reza Aryanto, Liza Fernanda Letlora.(2019), Kebutuhan Alat Gali Muat dan Alat Angkut Untuk Mencapai Target Produksi pada Grasberg, PT Freeport Indonesia. Indonesian Mining and Energy Journal, Vol. 2 No.1. Halaman 24-30.
Saputra Ridwan, Yoszi Mingsi Anaperta. (2021) Evaluasi Kinerja Alat Gali Muat dan Alat Angkut Menggunakan Metode Quality Control Circle Untuk Mencapai Target Produksi Batubara Pada Tambang Terbuka PT Allied Indo Coal Jaya, Parambahan, Sawahlunto. Jurnal Bina Tambang, Vol. 6, No. 3.. Page 1-7.
Sefrizni, Arie dan Tamrin Kasim. (2019), Analisis Kebutuhan Alat Gali Muat dan Alat Angkut Menggunakan Simulasi Teori Antrian pada Produski Overburden di PT Haswi Kencana Indah, Kecamatan Sumay, Kabupaten Tebo, Provinsi Jambi. Jurnal Bina Tambang, Vol. 4, No. 3. Halaman 260-270.
Sutanto Hidayat, T. Iskandar, F.F. Ludiantoro, M. Wijayaningtyas. (2019) Heavy Equipment Efficiency, Productivity and Compatibility of Coal Mine Overburden Work In East Kalimantan. International Journal of Mechanical Engineering and Technology, Vol. 10, Issue 06. Page 194-202.
T. Khurrahman, E. Ibrahim, A. Rahman. (2019), Perencanaan Alat Gali Muat dan Alat Angkut pada Produksi Batubara 20.000.000 Ton di PT Bumi Merapi Energi . Jurnal Pertambangan, Vol. 3, No. 4.. Page 38-43.
Yanto Indonesianto, (2005), Pemindahan Tanah Mekanis, Jurusan Teknik Pertambangan, UPN “Veteran”, Yogyakarta
Yonal Ferdian, Ansosry.(2017) Estimasi Kebutuhan Peralatan Tambang Batubara untuk Mencapai Target Produksi pada Tahun 2017 PT Partner Resource Indonesia Jobsite Sungai Lilin, Provinsi Sumatera Selatan. Jurnal Bina Tambang, Vol. 3, No. 3. Page 1024-1033.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2024 Venus: Jurnal Publikasi Rumpun Ilmu Teknik
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.