Percepatan Proyek pada Schedule Penjadwalan Kapal Perang dengan Precedence Diagram Method di Perusahaan Galangan Kapal Surabaya
DOI:
https://doi.org/10.61132/jupiter.v3i2.766Keywords:
Precedence, Diagram, Method, Project, ManagementAbstract
The Shipyard Company is a company that operates in the shipping sector, including ship production, overhaul and ship maintenance. In this case, the Shipbuilding Company has an important role in providing quality and timeliness in every project that has been accepted. Quality and timeliness are closely related to the planned production schedule, with efficient and effective scheduling it will have an impact on the quality results and production progress carried out, and cut excess production costs. Based on these needs, an analysis was carried out using the Precedence Diagram Method (PDM) on the Install Machinery Engine Deck 1 sub-job on the Warship project. The data needed in this research is the work breakdown structure (WBS). Based on the analysis that has been carried out, it was found that the most efficient path was found by eliminating dummy factors, so that work can be carried out simultaneously without waiting for previous work. In this case, it was found that the processing time for the Install Machinery Engine Deck 1 work on the Warship project was 471 days, compared to 657 days previously. Thus, the conclusion of this research is that the PDM method schedule has more efficient results than previous planning.
References
Atin, S., & Cahyana, N. (2016). Pemanfaatan Precedence Diagram Method (PDM) dalam penjadwalan proyek di PT. X. Jurnal Ilmiah Teknik Sipil, 2, 29–36.
Elfira Safitri, S., Sri Basriati, & Latifah Hanum. (2019). Optimasi penjadwalan proyek menggunakan CPM dan PDM (Studi Kasus: Pembangunan Gedung Balai Nikah dan Manasik Haji KUA Kecamatan Kateman Kabupaten Indragiri Hilir). Jurnal Sains Matematika Dan Statistika, 5(2), 17–25.
I Gusti Ngurah Oka Suputra. (2011). Penjadwalan proyek dengan Precedence Diagram Method (PDM) dan Ranked Position Weight Method (RPWM). Jurnal Ilmiah Teknik Sipil, 15(1), 18–28.
Niland, N., Pearce, A. P., Naumann, D. N., O’Reilly, D., Series, P. B., Sataloff, R. T., Johns, M. M., Kost, K. M., Orsini, R. J., Medicine, T., Kalkman, J. P., Sataloff, R. T., Johns, M. M., Kost, K. M., Maiti, Bidinger, Assistance, H., Mitigate, T. O., Eroukhmanoff, C., & Licina, D. (2020). No 主観的健康感を中心とした在宅高齢者における健康関連指標に関する共分散構造分析Title. Global Health, 167(1), 1–5. https://www.e-ir.info/2018/01/14/securitisation-theory-an-introduction/
Nurhidayat, A., Arianto, B., & Bhirawa, D. A. N. W. T. (2013). Optimalisasi pembangunan proyek apartemen SGC Cibubur dengan menggunakan metode Precedence Diagram Method (PDM). Jurnal TeknikIndustri, 10(1), 22–32. https://doi.org/10.35968/jtin.v10i1.706
Octavia, D. M., Angri, W., & Citra, U. (2020). Analisis resource leveling menggunakan network planning pada pembangunan Rusunawa Institut Teknologi Padang. Progress in Civil Engineering Journal, 2(1), 20–30.
Putri, N. L., & Wijaya, A. F. (2023). Information technology risk management in educational institutions using ISO 31000 framework. Journal of Information Systems and Informatics, 5(2), 630–649. https://doi.org/10.51519/journalisi.v5i2.468
Regatama, G., dkk. (2019). Analisis network planning reparasi kapal SPB TITAN 70 dengan metode Critical Path Method. Jurnal Teknik Perkapalan, 5(2), 421–430.
Rusnani, E., Tukidi, & Haryanto, E. (2021). Journal of Scientech Research and Development, 3(1), 24–32. https://idm.or.id/JSCR/index.php/JSCR/article/view/14
Saputra, L. I., Budiarto, U., & Jokosisworo, S. (2017). Studi penjadwalan ulang, produktivitas, dan alokasi sumber daya manusia pada pekerjaan reparasi kapal MT. Asumi XXVI dengan network planning dan Critical Path Method. Teknik Perkapalan, 5(2), 421–430.
Sinaulan, M. J., Pratasis, P. A. K., & Arsjad, T. T. (2023). Optimalisasi waktu pembangunan ruas jalan dengan metode PDM (Precedence Diagram Method) pada proyek pembangunan ruas jalan Mantehage Buhias. Tekno, 21(85). https://ejournal.unsrat.ac.id/v3/index.php/tekno/article/view/49898%0Ahttps://ejournal.unsrat.ac.id/v3/index.php/tekno/article/view/49898/43429
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2025 Jupiter: Publikasi Ilmu Keteknikan Industri, Teknik Elektro dan Informatika

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.